Which is true of a finish-to-finish dependency?
A) It is a dependency in which the "from" activity cannot start until the "to" activity or successor is started.
B) It is a dependency in which in which the "from" activity must finish before the "to" activity or successor can start.
C) It is a dependency in which the "from" activity must be finished before the "to" activity can be finished.
D) It is a dependency in which the "from" activity must start before the "to" activity can be finished.
Correct Answer:
Verified
Q44: What term is used for the amount
Q45: Which dependencies do AOA network diagrams use?
A)
Q46: In project schedule management, the main goal of which
Q47: Which technique involves network diagramming and is used primarily
Q48: Which type of dependencies are inherent in
Q50: Which network diagramming technique uses boxes to
Q51: What is the latest possible time an
Q52: The critical path is the _ path
Q53: Which dependencies involve relationships between project and
Q54: What term is used for the amount
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents