The overriding objective of line-balancing is
A) to split operations between different stations so as to minimize the number of stations.
B) to achieve a balance of production resources that can deliver the right amount of production to satisfy demand requirements with minimum waste of resources.
C) to be clever about process design so as to achieve cycle time reduction with minimum defectives.
D) none of the above
Correct Answer:
Verified
Q53: It is easy to increase cycle time
Q54: Operational decisions made on the plant floor
Q55: With respect to the O.O.D.A.loop,fighter pilots must
Q56: Stochastic line-balancing problems are related to queuing
Q57: _ is the interval of time that
Q59: Cycle times of inbound and outbound supplies
Q60: Strategic thinking should include time-based and cycle-time
Q61: Which of the following is the first
Q62: Which of the following heuristics sets the
Q63: _ create bottlenecks that cause disruptive backups
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents