What is the critical path in a PERT/CPM diagram?
A) The chain of activities that takes the longest time to proceed through the network
B) The chain of activities that contains the greatest amount of slack
C) The chain of activities that contains the largest number of nodes
D) The chain of activities with the earliest finish time
E) The chain of activities with the fewest nodes
Correct Answer:
Verified
Q43: Which of the following is a characteristic
Q44: The concept of "lift" as proposed by
Q45: When examining a project budget, what is
Q46: Why are project teams becoming more popular?
A)They
Q47: In identifying the right members for a
Q49: What project management tool shows the total
Q50: Although measuring and monitoring performance is crucial
Q51: What project management tool is most popular
Q52: In deciding on performance measures, organizations need
Q53: Because it is often very difficult and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents