An organization planned to use $44 of material per unit of activity but it actually used $42 of material per unit of activity,and it planned to make 1,200 units but it actually made 1,000 units.The flexible budget amount for materials is:
A) $42,000.
B) $44,000.
C) $48,000.
D) $49,400.
Correct Answer:
Verified
Q80: In zero-based budgeting:
A)the prior year's budgeted amounts
Q81: A favorable cost variance of significant magnitude:
A)is
Q82: All of the following are true of
Q83: The use of low-quality raw materials is
Q84: The variance that LEAST affects cost control
Q86: The role of budgeting in planning and
Q87: The variances that should be investigated by
Q88: A favorable efficiency variance for direct labor
Q89: If standards are lax,cost variances will tend
Q90: Planning variances are the focus of cost
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents