The variances that should be investigated by management include:
A) only unfavorable variances.
B) only favorable variances.
C) all variances, both favorable and unfavorable.
D) both favorable and unfavorable variances that are considered significant in amount for the company.
Correct Answer:
Verified
Q82: All of the following are true of
Q83: The use of low-quality raw materials is
Q84: The variance that LEAST affects cost control
Q85: An organization planned to use $44 of
Q86: The role of budgeting in planning and
Q88: A favorable efficiency variance for direct labor
Q89: If standards are lax,cost variances will tend
Q90: Planning variances are the focus of cost
Q91: A flexible budget variance is $1,500 favorable
Q92: The PRIMARY reason for using cost variances