There are four resources and four jobs to be done. Assume there must be one-to-one matching between jobs and resources. The time required for each resource to do each job is as follows:
What is the optimal assignment of resources to jobs?
A) 1 to A; 2 to C; 3 to B; 4 to D
B) 1 to B; 2 to D; 3 to C; 4 to A
C) 1 to C; 2 to B; 3 to A; 4 to D
D) 1 to D; 2 to B; 3 to C; 4 to A
E) 1 to A; 2 to C; 3 to D; 4 to B
Correct Answer:
Verified
Q70: Scheduling in service systems may involve scheduling:
(I)the
Q73: For the jobs listed below, which processing
Q74: The following table contains information about
Q75: The president of a consulting firm wants
Q76: There are four resources and four
Q78: The owner/operator of the local franchise
Q79: The president of a consulting firm wants
Q80: A major difference between manufacturing and service
Q81: Eva, the owner of Eva's Second
Q82: The owner/operator of the local franchise
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents