A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet a schedule of 400 units per day. The tasks necessary to produce this product are detailed in the table below.
a. Draw the network described in the table.
b. Without regard to a production schedule, what is the minimum possible cycle time (in seconds) for this situation; what is the maximum?
c. What is the required cycle time (in seconds) in order to meet the schedule?
d. What is the theoretical minimum number of workstations needed to meet the schedule?
e. Balance this line using longest processing time.
f. What is the efficiency of the balance obtained in part e?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q92: A work cell is scheduled to build
Q139: What is the role of heuristics in
Q140: Define the following terms that occur in
Q141: You have been asked to balance
Q142: An insurance claims processing center has
Q143: An assembly line with 11 tasks is
Q145: A facility is trying to set
Q146: Brandon's computer shop has hired a consultant
Q148: There are three work centers (A,
Q307: Assembly line balancing has just been used
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents