An Electronics Manufacturer Makes Remote Control Devices for Interactive-Cable-TV Systems

Question 150

Essay

An electronics manufacturer makes remote control devices for interactive-cable-TV systems. The following assembly tasks must be performed on each device.
 Task  Description  Predecessor(s)  Time (min)  A  Place circuit into circuit frame 0.50 B  Solder circuit connections to central circuit  control  A 0.70 C  Place circuit assembly in device frame  B 0.40 D  Attach circuit assembly to device frame  C 0.30 E  Place and attach display to frame 0.30 F  Place and attach keypad to frame 0.20 G  Place and attach top body of device to frame  E, F 0.35 H  Place and attach battery holder to frame  D 0.40 I  Place and attach bottom body of device to  G, H 0.60 frame J Test device  I0.30\begin{array}{|c|l|c|c|}\hline \text { Task } &\text { Description } &\text { Predecessor(s) } & \text { Time (min) }\\\hline \text { A } & \text { Place circuit into circuit frame } & -- & 0.50 \\\hline \text { B } & \begin{array}{l}\text { Solder circuit connections to central circuit } \\\text { control }\end{array} & \text { A } & 0.70 \\\hline \text { C } & \text { Place circuit assembly in device frame } & \text { B } & 0.40 \\\hline \text { D } & \text { Attach circuit assembly to device frame } & \text { C } & 0.30 \\\hline \text { E } & \text { Place and attach display to frame } & -- & 0.30 \\\hline \text { F } & \text { Place and attach keypad to frame } & -- & 0.20 \\\hline \text { G } & \text { Place and attach top body of device to frame } & \text { E, F } & 0.35 \\\hline \text { H } & \text { Place and attach battery holder to frame } & \text { D } & 0.40 \\\hline \text { I } & \text { Place and attach bottom body of device to } & \text { G, H } & 0.60 \\&\text { frame } \\\hline\mathrm{J} &\text { Test device } & \text { I} & 0.30\\\hline\end{array}
a. Draw the precedence diagram for this problem.
b. What is the sum of the task times?
c. What cycle time will allow the production of 200 units over a ten-hour day?
d. What is the theoretical number of workstations needed?
e. Balance this assembly line using the heuristic most following tasks and the heuristic longest operation time.
f. How do these two solutions differ?
Which do you prefer; why?

Correct Answer:

verifed

Verified

The sum of the task times is 4.05 minute...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents