Which of the following statements is true regarding the critical path of a PERT network?
A) It refers to the sequence of events and activities requiring the shortest period of time to complete.
B) A delay in completing the sequences in the critical path causes no delay in completing the project.
C) It plays a negligible role in controlling the completion time of the project.
D) It provides an insight into how the unrealistic features of a schedule can be modified.
E) It is essentially a bar graph mainly used for scheduling resources.
Correct Answer:
Verified
Q77: Which of the following activities is carried
Q78: What can managers do to prevent products
Q79: Sales during the _ stage is typically
Q80: Which of the following is a characteristic
Q81: In a PERT network, a(n) _ is
Q83: Explain the concept of input planning.
Q84: Which scheduling tool is typically used to
Q85: In a PERT network, the sequence of
Q86: Which of the following is true regarding
Q87: The two primary elements of a PERT
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents