Forward Scheduling Establishes a Project Start Date and Then Schedule

Question 34

True/False

Forward scheduling establishes a project start date and then schedule forward from that date. Based on the planned duration of required tasks, their interdependencies and the allocation of resources to complete those tasks, a projected project completion date is calculated.