Elapsed time measures the actual amount of time that it takes to complete a task, taking into account that workers cannot possibly perform at 100% efficiency, and that interruptions increases the amount of time it takes from start to finish to complete a task.
Correct Answer:
Verified
Q26: Scope defines both the boundaries of what
Q27: Joint project planning (JPP) is a hierarchical
Q28: Optimistic duration is the estimation of the
Q29: Optimistic duration is the estimation of the
Q30: Pessimistic duration is the estimation of the
Q32: The expected duration of a task is
Q33: Milestones have no duration.
Q34: Forward scheduling establishes a project start date
Q35: Forward scheduling establishes a project deadline forward
Q36: The availability of resources, especially people and