As a Project Is Crashed from Its Normal Duration to Its

Question 1

Multiple Choice

As a project is crashed from its normal duration to its optimal duration, ????.


A) The project's indirect cost is reduced
B) The project's direct cost is reduced
C) The duration of the project increases
D) Additional float is created
E) None of the above