When There Is a Significant Increase in the Estimated Total

Question 19

Multiple Choice

When there is a significant increase in the estimated total contract costs but the increase does not eliminate all profit on the contract, which of the following is correct?


A) Under both the percentage-of-completion and the completed-contract methods, the estimated cost increase requires a current period adjustment of excess gross profit recognized on the project in prior periods.
B) Under the percentage-of-completion method only, the estimated cost increase requires a current period adjustment of excess gross profit recognized on the project in prior periods.
C) Under the completed-contract method only, the estimated cost increase requires a current period adjustment of excess gross profit recognized on the project in prior periods.
D) No current period adjustment is required.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents