The percentage-of-completion method must be used when certain conditions exist. Which of the following is not one of those necessary conditions?
A) Estimates of progress toward completion, revenues, and costs are reasonably dependable.
B) The contractor can be expected to perform the contractual obligation.
C) The buyer can be expected to satisfy some of the obligations under the contract.
D) The contract clearly specifies the enforceable rights of the parties, the consideration to be exchanged, and the manner and terms of settlement.
Correct Answer:
Verified
Q12: Repossessed merchandise as a result of a
Q13: When interest is involved in installment sales,
Q14: Which of the following is not an
Q15: The FASB concluded that if a company
Q16: Which of the following is not a
Q18: Cost estimates on a long-term contract may
Q19: When there is a significant increase in
Q20: Under the completed-contract method of accounting for
Q21: The Nathan Company is involved in the
Q22: Which of the following methods or bases
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents