Is it possible for the members of the Project Board to provide guidance to the Project Manager outside the standard documentation/reporting procedures specified in PRINCE2?
A) No. Communication from the Project Board must always occur at predefined points.
B) Yes, but only in response to a PRINCE2 report from the Project Manager.
C) Yes, but only if the Project Manager specifically requests guidance.
D) Yes. They are allowed to give ad-hoc direction any time they like.
Correct Answer:
Verified
Q76: Which of the following should always be
Q77: The principle of Learning from Experience dictates
Q78: Which is longer, the product life span
Q79: If there is more than one version
Q80: When a project is closed, all project
Q82: During which process is the request to
Q83: Which role is responsible for drafting the
Q84: The purpose of Configuration Management is:
A)To create
Q85: According the Prince2 principles, the scope of
Q86: Which of the following do progress controls
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents