If there is more than one version of a document in circulation, what action should the Project Manager take?
A) Create a new version of the document and issue it to everybody.
B) Halt work until the correct version can be identified.
C) Recall all versions of the document.
D) Request a Product Status Account.
Correct Answer:
Verified
Q74: Which role is responsible for defining and
Q75: Which of the following is true about
Q76: Which of the following should always be
Q77: The principle of Learning from Experience dictates
Q78: Which is longer, the product life span
Q80: When a project is closed, all project
Q81: Is it possible for the members of
Q82: During which process is the request to
Q83: Which role is responsible for drafting the
Q84: The purpose of Configuration Management is:
A)To create
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents