Josh is a program manager who likes to keep on top of things at You Want It - We Build It Industrial. So when he's telling his project managers to prep project plans for each project based on the most current and available information, having them make changes as new information comes in, what technique is he using?


A) Delphi technique
B) Progressive elaboration
C) Continuous improvement
D) Slow start