Howard is creating a program WBS hierarchy for his program, Ferocious. Which of the following components is at the lowest level of his hierarchy?
A) Schedule activities
B) Program deliverables
C) Program packages
D) Work packages
Correct Answer:
Verified
Q44: Howard's program, Ferocious, has been approved. Now,
Q45: Lori has been asked to create a
Q46: Which of the following processes does not
Q47: What is program scope definition?
A)A deliverable-oriented plan
Q48: Which of the following is part of
Q50: Adam is creating program schedule. He is
Q51: You asked your friend Dixon, a program
Q52: Which of the following structures displays the
Q53: Josh is a program manager who likes
Q54: Which of the following is stage two