A Punch List Includes

Question 3

Multiple Choice

A punch list includes


A) items considered still open and in need of attention before project termination
B) items checked off and considered completed
C) items to be addressed after the project has been officially closed out
D) items recommended by the contractor for the customer's future consideration

Correct Answer:

verifed

Verified