Which one of the following is true about project termination and close-out:


A) it happens automatically upon customer approval of the end-item
B) it requires the same degree of thoughtful attention by the project manager as other aspects of the project
C) termination and close-out activities are the responsibility of the customer
D) it happens upon delivery and installation of the end-item

Correct Answer:

verifed

Verified