Solved

In a Start-To-Start Relationship, a 2-Day Lag Implies That

Question 13

Multiple Choice

In a start-to-start relationship, a 2-day lag implies that:


A) the successor should not start until two days after the predecessor has been completed.
B) the successor should not start until two days after the predecessor has started.
C) the successor can start two days before the predecessor has started.
D) the two activities can start on the same date.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents