If Activity A has to be performed before Activity B can start, then:
A) A is a predecessor to B.
B) B is a predecessor to A.
C) there is a discretionary dependency or external dependency between A and B.
D) the relationship between A and B can only be indicated on an AON network.
Correct Answer:
Verified
Q6: The early expected start time, ES, of
Q7: The latest allowable finish time that an
Q8: Doing a project fast has the following
Q9: The advantages of scheduling include all of
Q10: The following technique requires the use of
Q12: The critical path:
A) is shortest path through
Q13: In a start-to-start relationship, a 2-day lag
Q14: The criticism of network techniques that some
Q15: Resource leveling:
A) makes use of float (slack)
Q16: The forward and backward pass:
A) determine the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents