If an activity has two immediate successors and their late start times are 26 and 33, respectively, then the late finish time of that activity must be:
A) 26
B) 33
C) cannot be determined from this information
Correct Answer:
Verified
Q1: If an activity has two immediate predecessors
Q3: Which one of the following statements is
Q4: In a network, the critical path is
Q5: In a network, the critical path indicates:
A)
Q6: The early expected start time, ES, of
Q7: The latest allowable finish time that an
Q8: Doing a project fast has the following
Q9: The advantages of scheduling include all of
Q10: The following technique requires the use of
Q11: If Activity A has to be performed
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents