Given that activity B has the following times, which of the following statements is true about activity B?
Earliest start time = 9 days; latest start time = 17 days; earliest finish time = 15 days; latest finish time = 23 days
A) Activity B has a slack time of 8 days.
B) Activity B is a critical activity.
C) Activity B takes 6 days to complete.
D) Activity B takes 23 days to complete.
Correct Answer:
Verified
Q48: Which of the following is not a
Q49: Popular techniques to plan for and monitor
Q50: Activity times for a project can be
Q51: Which one of the following statements best
Q52: A project has three possible paths from
Q54: Which of the following is the critical
Q55: What is the project duration for the
Q56: Using the information shown in the
Q57: Using the information shown in the previous
Q58: Using the information shown in the previous
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents