A project has three possible paths from start to finish. Path A-B-C is 15 hours; path A-C-D is 10 hours, and path A-C-E is 20 hours. Which one of the following statements is true?
A) The expected duration of this project is 10 hours.
B) The expected duration of this project is 15 + 10 + 20 = 45 hours.
C) Path A-C-E is the critical path.
D) Path A-B-C has the most slack.
Correct Answer:
Verified
Q47: If we cannot estimate probabilities because the
Q48: Which of the following is not a
Q49: Popular techniques to plan for and monitor
Q50: Activity times for a project can be
Q51: Which one of the following statements best
Q53: Given that activity B has the following
Q54: Which of the following is the critical
Q55: What is the project duration for the
Q56: Using the information shown in the
Q57: Using the information shown in the previous
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents