A Company Is Faced with a Project of Implementing a New

Question 45

Essay

A company is faced with a project of implementing a new ERP system.The information on activity precedence,time,and cost is given below (time in weeks).
 Activity  Predecessor(s)  Standard  Time  Crash  Time  Standard  Cost  Crash  Cost  Crash  Cost/Wk  A  none 97$700$1100$200 B  A 76$600$750$150 C  A 53$500$1000$250 D  B 42$550$800$125 E  C 65$800$900$50 F  D,E 53$700$1000$150 G  D 86$1000$1200$100\begin{array} { | l | l | r | r | r | r | r | } \hline \text { Activity } & \text { Predecessor(s) } & \begin{array} { l } \text { Standard } \\\text { Time }\end{array} & \begin{array} { l } \text { Crash } \\\text { Time }\end{array} & \begin{array} { l } \text { Standard } \\\text { Cost }\end{array} & \begin{array} { l } \text { Crash } \\\text { Cost }\end{array} & \begin{array} { l } \text { Crash } \\\text { Cost/Wk }\end{array} \\\hline \text { A } & \text { none } & 9 & 7 & \$ 700 & \$ 1100 & \$ 200 \\\hline \text { B } & \text { A } & 7 & 6 & \$ 600 & \$ 750 & \$ 150 \\\hline \text { C } & \text { A } & 5 & 3 & \$ 500 & \$ 1000 & \$ 250 \\\hline \text { D } & \text { B } & 4 & 2 & \$ 550 & \$ 800 & \$ 125 \\\hline \text { E } & \text { C } & 6 & 5 & \$ 800 & \$ 900 & \$ 50 \\\hline \text { F } & \text { D,E } & 5 & 3 & \$ 700 & \$ 1000 & \$ 150 \\\hline \text { G } & \text { D } & 8 & 6 & \$ 1000 & \$ 1200 & \$ 100 \\\hline\end{array}
The company would like to determine which activities to crash and by how much in order to
complete the ERP implementation in 24 weeks.Using linear programming and Excel Solver,find
the best solution

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents