Question 49

Essay

Use this information to answer the following questions.
A university needs to prepare a banquet for its graduating seniors.The following information describes the relationships between the activities that need to be completed for this banquet.
 Immediate  Activity  Predecessors  A  B  C  A, B  D  C  E  C  F  D, E  G  E  H  F, G \begin{array} { c l l } & \text { Immediate } \\\text { Activity } & \text { Predecessors } \\ \text { A } & - \\\text { B } & - \\\text { C } & \text { A, B } \\\text { D } & \text { C } \\\text { E } & \text { C } \\\text { F } & \text { D, E } \\\text { G } & \text { E } \\\text { H } & \text { F, G }\end{array}
-Refer to the information above.Assume that the catering manager was able to estimate the number of hours needed to complete each activity as follows.
 Activity  Optimistictime  Most Likely Time  Pessimistic Time  A 235 B 467 C 345 D 235 E 123 F 5711 G 689 H 467\begin{array} { c c c c } \text { Activity } & \text { Optimistictime } & \text { Most Likely Time } & \text { Pessimistic Time } \\ \text { A } & 2 & 3 & 5 \\\text { B } & 4 & 6 & 7 \\\text { C } & 3 & 4 & 5 \\\text { D } & 2 & 3 & 5 \\\text { E } & 1 & 2 & 3 \\\text { F } & 5 & 7 & 11 \\\text { G } & 6 & 8 & 9 \\\text { H } & 4 & 6 & 7\end{array}
Determine the probability that the project will be completed in
a.Less than 25 hours.
b.Greater than 25 hours.
c.Less than 27 hours.
d.Greater than 27 hours.

Correct Answer:

verifed

Verified

\[\begin{array} { | l | c | }
\hline \t...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents