A project has a ??? of $850,000. The project manager has identified and documented that certain key applications were not included in the scope management plan. As reported, the CPI is 0.8, and the PMO allows only a 5% additional increment to the planned budget. Which of the following should the project manager do NEXT?
A) Add the required work to complete the project behind $892,500.
B) Evaluate the impact and justify adding new work to the project.
C) Obtain approval from the CCB.
D) Request a budget increase of $170,000.
Correct Answer:
Verified
Q234: A team member was assigned a new
Q235: Which of the following is a team-building
Q236: An outsourced project team member approaches the
Q237: A new high-priority project is assigned to
Q238: A governance committee has just approved a
Q240: A project manager is informed that a
Q241: A project manager is required to maintain
Q242: Which of the following activity sequencing techniques
Q243: Which of the following analyses should a
Q244: A project team is in the process
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents