A New High-Priority Project Is Assigned to the Project Manager

Question 237

Multiple Choice

A new high-priority project is assigned to the project manager with a fully formed budget, deadline, and scope. The project manager is creating the project schedule. A new high-priority project is assigned to the project manager with a fully formed budget, deadline, and scope. The project manager is creating the project schedule.   Which of the following calculations accurately shows the critical path? A)  20 days B)  39 days C)  49 days D)  52 days Which of the following calculations accurately shows the critical path?


A) 20 days
B) 39 days
C) 49 days
D) 52 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents