A Scrum team failed to meet the Sprint objectives. One of the key members of the team fell ill and was away for two days right at the beginning of the four week Sprint. What is the most likely reason that the team did not meet the Sprint objectives?
A) The Product Owner is unable to prioritize.
B) The team is lacking skills.
C) The team did not plan the Sprint effectively.
D) The team is over-worked.
Correct Answer:
Verified
Q2: What is an information radiator?
A) A physical
Q3: How should 'done' be defined when multiple
Q4: What is the best way to split
Q5: When is a Sprint complete?
A) When all
Q6: What message can you give to a
Q7: What is a characteristic of a well-designed
Q8: The Product Owner is going on a
Q9: A large product team features six different
Q10: During the release planning meeting, it is
Q11: What is time-boxing?
A) A period of intense
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents