With the ____ method of estimating, a certain unit that is common to all projects of this type is selected and the number of these units is calculated for each project.
A) price per unit
B) single-rate
C) piece
D) job
Correct Answer:
Verified
Q5: _ estimation methods include price per typical
Q6: The _ of the building is calculated
Q7: Preliminary estimating methods can be used to
Q8: Estimators typically turn to preliminary estimating methods
Q9: Using the price per unit estimating method
Q11: Assembly estimating can be a powerful cost
Q12: Using the _ method, a building, which
Q13: Which of the following is NOT a
Q14: The _ is defined as the area
Q15: _ estimating methods include the price per