Services
Discover
Homeschooling
Ask a Question
Log in
Sign up
Filters
Done
Question type:
Essay
Multiple Choice
Short Answer
True False
Matching
Topic
Engineering
Study Set
Fundamentals of Construction Estimating
Quiz 15: Closing the Bid
Path 4
Access For Free
Share
All types
Filters
Study Flashcards
Practice Exam
Learn
Question 1
Multiple Choice
A bid may sometimes be called a(n) "____" or a "proposal."
Question 2
Multiple Choice
Most contractors use a ____ sheet to gather together all of the constituent prices of the estimate.
Question 3
Multiple Choice
A construction contract bid is compiled in three stages: the advance stage, the review stage, and the ____ stage.
Question 4
True/False
In the bid markup, profit is generally assessed as a compensation for the risk taken by the contractor.
Question 5
True/False
The first step in the cost control process is assembling cost data for use in estimating future jobs.
Question 6
True/False
The recap format for the takeoff items of a unit- price bid is the same as the format used with a lump-sum bid.
Question 7
Multiple Choice
The last stage in the preparation of a unit-price bid is to ____.
Question 8
True/False
Contractors seldom see an advantage in allowing a higher proportion of overheads and fee against the work being completed early in the project.
Question 9
True/False
Add-ons for small tools and payroll additives are calculated as a percentage of the total labor amount of the bid.
Question 10
Multiple Choice
____ are quoted for proposed changes in the specifications.
Question 11
Multiple Choice
A construction bid contract is compiled in three stages which include all of the following EXCEPT the _____ stage.
Question 12
Multiple Choice
The information on a ____ is generally requested to provide a basis for evaluating monthly progress payments on the project.
Question 13
Multiple Choice
____ is defined as the amount of money remaining after all project expenses and company expenses have been paid.
Question 14
True/False
The estimate-cost control process is linear in nature.
Question 15
Multiple Choice
A stipulated sum of money to be expended by a contractor on a specific work item on a project is usually referred to as a ____.
Question 16
True/False
At the very start of the estimating process, the estimator can set up the summary sheet by checking off the trades that will be completed by "own forces" and those that will be subcontracted.
Question 17
True/False
Most contractors use a standard format of summary to capture all the main components of an estimate.
Question 18
Multiple Choice
Whereas lump-sum bids involve calculating a single final price and assembling a list of subtrades, with a unit-price bid, the contractor is also required to complete a "_______", that is, an itemized breakdown of the work of the project.