Solved

Review the PERT Network Below: If It Takes 1, 2

Question 320

Multiple Choice

Review the PERT Network below: If it takes 1, 2, or 3 weeks for each activity (represented by a box) to be completed, the critical path is represented by:   Review the PERT Network below: If it takes 1, 2, or 3 weeks for each activity (represented by a box)  to be completed, the critical path is represented by:       A)  the path that begins with  Start  and continues with all boxes labeled with No. 1. B)  the path that begins with  Start,  continues with all boxes labeled with No. 2, and concludes with  Finish.  C)  the path that begins with  Start,  continues with one box labeled with No. 2, proceeds with all boxes labeled with No. 3, and concludes with  Finish.  D)  the path that begins with  Start,  continues with all boxes labeled with No. 1, and concludes with  Finish.  


A) the path that begins with "Start" and continues with all boxes labeled with No. 1.
B) the path that begins with "Start," continues with all boxes labeled with No. 2, and concludes with "Finish."
C) the path that begins with "Start," continues with one box labeled with No. 2, proceeds with all boxes labeled with No. 3, and concludes with "Finish."
D) the path that begins with "Start," continues with all boxes labeled with No. 1, and concludes with "Finish."

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents