Solved

Cassandra Was Planning a New Product Launch

Question 315

Multiple Choice

Cassandra was planning a new product launch. She knew that the art department was ready to work on the promotional pieces now, but they couldn't start until the marketing strategy group established the price point and the purchasing department obtained the paper needed to design the promotional piece. Establishing price points would take about a week and was dependent on manufacturing getting the costs to the marketing strategy group. This was expected a week from today. The purchasing group indicated the paper could be obtained locally the same day it was requested. Assuming things go as planned and based on this information, which of the following tasks could be as much as a week late without jeopardizing the deadline for the entire project?


A) marketing strategy's determination of the price point
B) manufacturing's determination of the costs
C) obtaining the paper
D) the art department taking a month-long vacation

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents