Question 81
Multiple Choice
Quality standards that will be used should also be stated and referenced in other appropriate project documents, such as technical specifications and acceptance criteria, and communicated to members of the project team
Question 82
Multiple Choice
To help assure quality, the project quality plan should contain written procedures for
Question 83
Multiple Choice
The work packages are at a level at which the wants to monitor and control the budget, and can collect data on actual costs and the value of the work completed during the performance of the project.
Question 84
Multiple Choice
A comprehensive project scope document is the work breakdown structure.
Question 85
Multiple Choice
The project team or contractor must avoid , which is informally making changes to the project scope without appropriate approval.
Question 86
Multiple Choice
In order to prevent poor quality and avoid quality problems, there needs to be
Question 87
Multiple Choice
The work packages are at a level can be assigned responsibility and accountability for achieving the work package.
Question 88
Multiple Choice
The all of the lowest-level work packages in the work breakdown structure constitutes completion of the project work scope.
Question 89
Multiple Choice
The lowest-level work item of any one branch is called
Question 90
Multiple Choice
The at a level of a high degree of confidence that all the activities that need to be performed to produce the deliverable can be defined, the types and quantities of resources can be determined, and the associated activity durations and costs can be reasonably estimated.
Question 91
Multiple Choice
is a structured approach for organising all the project work and deliverables into logical groupings and subdividing them into more manageable components to help ensure that all the work and deliverables to complete the project are identified and included in the baseline project plan.
Question 92
Multiple Choice
Once the project scope document has been prepared and agreed on, the next step in the planning phase is to
Question 93
Multiple Choice
The WBS should be decomposed to a level that identifies individual work packages for
Question 94
Multiple Choice
The states the specific deliverable that is expected to be completed from the work activities associated with each lowest level work package.
Question 95
Multiple Choice
It is important to plan for in performing the project to assure that the work is done according to specifications and applicable standards and that deliverables meet acceptance criteria.