Positive slack indicates the maximum amount of time
A) that the activities on the critical path should be accelerated to complete the project by the required completion time.
B) that each of the activities in the project can be delayed without jeopardising completion of the project by the required completion time.
C) that the activities with the positive slack should be accelerated to complete the project by the required completion time.
D) that the activities on a particular path can be delayed without jeopardising completion of the project by the required completion time.
Correct Answer:
Verified
Q52: Latest start time (LS)is the latest time
Q58: Calculate the latest start for Task B
Q60: Total slack is sometimes called
A)drift.
B)ride.
C)float.
D)sink.
Q63: The total completion time is 25 days.Task
Q66: As a part of the scrum technique
Q67: If the planned corrective actions do not
Q68: The estimated duration for each activity is
Q72: A concentrated effort to accelerate project progress
Q74: Total slack is calculated for each of
Q87: The development team develops, delivers, and demonstrates
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents