When considering the availability of resources, it may be necessary to make some assumptions, such as
A) the unemployment rate in the community.
B) the ability to hire additional individuals with the appropriate expertise in time for when they will be required to work on a project.
C) the number of project deliverables.
D) the type of organisational structure of the sponsor.
Correct Answer:
Verified
Q23: Changes might be initiated by the customer
Q25: The amount of slack should determine the
Q28: It is necessary to monitor the progress
Q29: An updated project schedule can be generated
Q31: When the customer requests a change, the
Q33: The estimated duration for each activity must
Q35: It is important to know what types
Q37: When estimating the types and quantities of
Q38: People sometimes perform to expectations, their effort
Q40: When estimating resources for activities to estimate
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents