Solved

Which of the Following Is Determined as a Direct Result

Question 46

Multiple Choice

Which of the following is determined as a direct result of computing the earliest starting and finishing times for the activities of a project network?


A) expected project duration
B) activity slack time
C) which activities are on the critical path
D) variance in project duration
E) maximum project duration

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents