A hierarchical listing of what must be done in a project is called a
A) work breakdown structure (WBS) .
B) PERT.
C) planning matrix.
D) crashing plan.
E) critical path.
Correct Answer:
Verified
Q44: A method used for establishing a logical
Q45: The advantage a precedence diagram has over
Q46: Which of the following is determined as
Q47: Concerning PERT and CPM
A)These are two different
Q48: Consider the portion of a project depicted
Q50: Once a project is underway, the project
Q51: Which of the following is not true
Q52: Shortening activity durations is called
A)expediting.
B)crashing.
C)vendor management.
D)null nodes.
E)trade-off
Q53: Activity 7-8 is directly preceded by two
Q54: A sequence of activities that leads from
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents