Another name for total slack is free slack.
Free
True False
Answer:

Answer:

False

Tags
Choose question tag
close menu
arrow
Critical path tasks always have zero slack.
Free
True False
Answer:

Answer:

True

Tags
Choose question tag
close menu
arrow
AON and AOA networks can both be used to depict any project network.
Free
True False
Answer:

Answer:

True

Tags
Choose question tag
close menu
arrow
Networks are usually drawn with a "Start" node to the right and a "Finish" node to the left.
True False
Answer:
Tags
Choose question tag
close menu
arrow
The difference between EST and LFT is called slack.
True False
Answer:
Tags
Choose question tag
close menu
arrow
The difference between LFT and EFT is called slack.
True False
Answer:
Tags
Choose question tag
close menu
arrow
An event is a series of connected activities.
True False
Answer:
Tags
Choose question tag
close menu
arrow
A big advantage of AON networks is that they are easier to draw.
True False
Answer:
Tags
Choose question tag
close menu
arrow
There is more than one way to compute slack.
True False
Answer:
Tags
Choose question tag
close menu
arrow
When it was originally developed, PERT used certain (deterministic) methods to estimate activity duration.
True False
Answer:
Tags
Choose question tag
close menu
arrow
The difference between LST and LFT is called slack.
True False
Answer:
Tags
Choose question tag
close menu
arrow
The shortest time to complete a network is equal to the duration of the longest path through the network.
True False
Answer:
Tags
Choose question tag
close menu
arrow
A diagram of nodes connected by directional arcs that defines the project and illustrates the technical of all activities is referred to as a network.
True False
Answer:
Tags
Choose question tag
close menu
arrow
The difference between LFT and EFT is called free slack.
True False
Answer:
Tags
Choose question tag
close menu
arrow
Milestones are not depended upon the predecessor activities in the project plan.
True False
Answer:
Tags
Choose question tag
close menu
arrow
The difference between the LST and EST is called free slack.
True False
Answer:
Tags
Choose question tag
close menu
arrow
The difference between the LST and EST is called slack.
True False
Answer:
Tags
Choose question tag
close menu
arrow
Critical path tasks always have zero free slack.
True False
Answer:
Tags
Choose question tag
close menu
arrow
Standard Pert/CPM networks can be used to resolve probabilistic concerns.
True False
Answer:
Tags
Choose question tag
close menu
arrow
To manage a project successfully, the project manager need only pay close attention to tasks on the critical path.
True False
Answer:
Tags
Choose question tag
close menu
Showing 1 - 20 of 108