Lauren, a project manager, has a workload of 24,000 hours that needs to be completed in 30 weeks. She has a team of 20 people who work five 8-hour days per week. She notices that in the 30-week period, there are five holidays and 5 members have each requested 10 days off. Given this information, Lauren is _____ short of completing her workload.
A) 1,200 hours
B) 2,500 hours
C) 2,000 hours
D) 1,500 hours
E) 3,800 hours
Correct Answer:
Verified
Q53: Starting the building phase before the design
Q54: Which of the following rules maximizes the
Q55: William, a project manager, is trying to
Q56: Allocating specific, limited resources to specific activities
Q57: A task has a normal duration of
Q59: A limitation associated with traditional approaches to
Q60: Mark, the chief editor of a magazine,
Q61: The following describes which priority rule: This
Q62: What is resource loading?
Q63: The following describes which priority rule: With
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents