William, a project manager, is trying to figure out how many hours his team can work in a period of three months. After accounting for weekends, he notes that each member of the team can work for five 8-hour days per week. After consulting his calendar, he realizes that there are three public holidays in the next three months and two employees have each requested two separate weeks off. His team consists of 15 people. Given this information, William can allocate approximately _____ of work to his team.
A) 7,200 hours
B) 6,120 hours
C) 7,600 hours
D) 6,680 hours
E) 5,500 hours
Correct Answer:
Verified
Q50: The task duration with standard-practice resource usage
Q51: Multitasking speeds up project completion.
Q52: The shortest-task-first priority rule for assigning resources
Q53: Starting the building phase before the design
Q54: Which of the following rules maximizes the
Q56: Allocating specific, limited resources to specific activities
Q57: A task has a normal duration of
Q58: Lauren, a project manager, has a workload
Q59: A limitation associated with traditional approaches to
Q60: Mark, the chief editor of a magazine,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents