What is the fundamental difference between a fixed-price and a cost-plus contract?
A) On fixed-price contracts partnering is used while it is not used for cost-plus contracts.
B) On fixed-price contracts macro estimates are used while micro estimates are used for cost-plus contracts.
C) No scope changes are made on fixed-price contracts while scope changes are allowed for cost-plus contracts.
D) On fixed-price contracts the cost is set in advance while for cost-plus contracts it is established after the project is completed.
E) On fixed-price contracts contractors are used while on cost-plus contracts no external contractors are used.
Correct Answer:
Verified
Q51: When considering principled negotiation, both buyers and
Q52: What does the acronym BATNA stand for?
A)
Q53: Ultimate success of the project is determined
Q54: Long-term partnerships will provide all the following
Q55: Which of the following is suggested as
Q57: The result of team building among the
Q58: Customer satisfaction can be quantified by
A) perceived
Q59: Regarding outsourcing, the most effective way to
Q60: Which of the following is NOT a
Q61: Projects are more prone to conflict when
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents