The beta distribution is used in project management to:
A) calculate slack on activities not on the critical path.
B) calculate the probability that a project will be completed within its budget.
C) calculate pessimistic and optimistic activity times.
D) determine which activity should be crashed.
E) none of the these.
Correct Answer:
Verified
Q76: In PERT analysis, the identification of the
Q77: A network consists of the following list.
Q78: A network consists of the activities in
Q79: Which of the following statements concerning CPM
Q80: The PERT pessimistic time estimate is an
Q82: The expected activity time in PERT analysis
Q83: Analysis of a PERT problem shows the
Q84: A project being analyzed by PERT has
Q85: A contractor's project being analyzed by PERT
Q86: Which of the following statements regarding PERT
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents