Question 41
True/False
Gross material requirements do not take into account the amount of inventory on hand.
Question 42
Multiple Choice
An order for 110 units of Product M has been placed. There are currently 30 units of Product M on hand. Each M requires 4 units of Component N. There are 50 units of N on hand. What are the net requirements for N?
Question 43
Multiple Choice
Which of the following statements regarding the gross material requirements plan is TRUE?
Question 44
Essay
Fourteen A washers, five B washers, three C washers, two D bolts, and eight E bolts are required to make one grill parts kit. If 100 grill parts kits are needed, how many more washers will be consumed than bolts?
Question 45
Essay
A manufacturing company is trying to determine the cost of materials used to produce an A. If Ds cost $3 and Fs cost $5, how much does it cost to produce an A (in D and F materials only)?
Question 46
Essay
Consider the following product structure. Forty units of Product A are needed. How many units of B, C, D, E, F, and G are needed?
Question 47
Multiple Choice
An order for 50 units of Product A and 60 of B has been placed. There are currently 25 units of Product B on hand. Each A requires 2 units of Part C; each B requires 5 units of C. There are 160 units of C available. What are the net requirements for C?
Question 48
True/False
A material requirements planning system generates output reports such as bill of material, inventory and purchase records, and lead times for each item.
Question 49
Multiple Choice
A material requirements plan contains information with regard to all of the following EXCEPT:
Question 50
Essay
________ are the result of adjusting gross requirements for inventory on hand and scheduled receipts.
Question 51
Essay
Explain the difference between a gross requirements plan and a net requirements plan.
Question 52
Essay
Each R requires 3 of component S and 3 of material A; each S requires 3 of part T. The lead time for assembly of R is 1 week. The lead time for the manufacture of S is 2 weeks. The lead time for material A is 1 week. The lead time for the procurement of T is 4 weeks. Construct the time-phased product structure.
Question 53
Multiple Choice
In MRP, the number of units projected to be available at the beginning of each time period refers to:
Question 54
Multiple Choice
It is week 1 and there are currently 20 As in stock. We need 300 As at the start of week 5. If there are scheduled receipts planned for week 3 and week 4 of 120 As each and A has a lead time of 2 weeks, when and how large of an order should be placed to meet the requirement of 300 As?
Question 55
Essay
Each X requires 2 of component Y and 1 of part W. Each Y requires 10 of Z. Each W requires 3 of Q and 2 of R. Lead times are X = 1 week, Y = 1 week, W = 2 weeks, R = 1 week, Z = 3 weeks, and Q = 3 weeks. Construct the time-phased product structure.
Question 56
Multiple Choice
Which of the following best describes a gross material requirements plan?
Question 57
Essay
Construct a product structure tree for a movie purchased in DVD format. Assume that it contains a single DVD disk. Don't be concerned with artwork-you may use labeled boxes for your parts and assemblies.
Question 58
Multiple Choice
An order for 100 units of Product A has been placed. There are currently 60 units of Product A on hand. Each A requires 4 units of Part B. There are 20 units of B available. What are the net requirements for B?