Average completion time for a schedule sequence at a work center is the ratio of:
A) total processing time to the number of jobs.
B) total flow time to total processing time.
C) total flow time to the number of jobs.
D) total processing time plus total late time to the number of jobs.
E) total flow time plus total late time to the number of jobs.
Correct Answer:
Verified
Q59: What is input-output control?
Q60: Three jobs are to be assigned to
Q61: Five jobs are waiting for processing through
Q62: Five welding jobs are waiting to be
Q63: EDD stands for what?
A) earliest due date
B)
Q65: Eight jobs have been sequenced at a
Q66: What does the use of the shortest
Q67: Sequencing (or dispatching):
A) assigns dates to specific
Q68: Which of the following dispatching rules ordinarily
Q69: Which of the following dispatching rules tends
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents