Table 7.14
You are responsible for managing a project with the following activities (times are given in weeks) .
-Using Table 7.14, what is the probability that the project will take 16 or more weeks to complete?
A) less than or equal to 20%
B) greater than 20% but less than or equal to 25%
C) greater than 25% but less than or equal to 30%
D) greater than 30%
Correct Answer:
Verified
Q129: A project manager hires a few new
Q130: _ is an attempt to reduce the
Q131: What options do project managers have to
Q132: A(n) _ identifies the key threats to
Q133: The project manager and team can step
Q134: To find the standard deviation of the
Q135: Assuming a beta distribution is being used,
Q136: Which of these steps comes first in
Q137: The _ is the shortest time in
Q138: A project tracking system should collect information
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents