Multiple Choice

The earliest start time for an activity is equal to the:
A) smallest earliest finish time of all of its immediate predecessors.
B) largest earliest finish time of all of its immediate predecessors.
C) smallest late start time of any of its immediate predecessors.
D) largest late finish time of all of its immediate predecessors.
Correct Answer:
Verified