
A project has three paths. A-B-C has a length of 25 days. A-D-C has a length of 15 days. Finally, A-E-C has a length of 20 days. Which one of the following statements is True?
A) A-D-C is the critical path.
B) A-B-C has the most slack.
C) The expected duration of this project is 25 days.
D) The expected duration of this project is 25 + 15 + 20 = 60 days.
Correct Answer:
Verified
Q29: A Gantt chart is a project schedule
Q30: Figure 7.2 Q31: The _ is the sequence of activities Q32: The earliest start time for an activity Q33: The earliest start time is never the Q35: Activity slack is defined as: Q36: Assume that activity G has the following Q37: Figure to accompany Table 7.1 Q38: Figure to accompany Table 7.1 Q39: Figure 7.1
A) latest start
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents