Quality control charts usually have a central line and upper and lower control limit lines. Which of the following is a reason that the process being monitored with the chart should be investigated?
A) A single point falls above or below the control limits.
B) Behavior is normal.
C) A large number of plots are on or near the central line.
D) There is no real trend in any direction.
E) There is a change in raw materials or operators.
Correct Answer:
Verified
Q42: You want to determine the control lines
Q43: If there are 12 total defects from
Q44: You want to develop a three-sigma R-chart.
Q45: You are going to develop an R-chart
Q46: You are going to develop an X-bar
Q48: Quality control charts usually have a central
Q49: For which of the following should we
Q50: For which of the following should we
Q51: You are developing an X-bar chart based
Q52: You want to determine the upper control
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents